How many days does it take to submit a request for an investment registration certificate for a BOT thermal power plant project?
Deadline for submitting documents requesting issuance of investment registration certificate for BOT thermal power plant projects is specified in Clause 1, Article 13 Circular 23/2015/TT-BCT Regarding issuance of investment registration certificates as follows:
Issuance of Investment Registration Certificate
1. Within thirty (30) days from the date of signing the investment agreement, the BOT Investor must submit to the Ministry of Planning and Investment a dossier requesting issuance of an Investment Registration Certificate.
2. Documents and procedures for issuance of Investment Registration Certificate are carried out in accordance with the provisions of Article 40 of Decree No. 15/2015/ND-CP dated February 14, 2015 of the Government on investment in the form of investment. public-private formula.
3. BOT investors are responsible for coordinating with relevant Vietnamese parties to explain opinions at the request of the Ministry of Planning and Investment.
Thus, according to the above regulations, the deadline for submitting documents requesting issuance of investment registration certificate for BOT thermal power plant projects is 30 days from the date of signing the investment agreement.